As at 21 August 2026Target completion Wk 34 · 24–28 Aug 202622 line items · 7 workstreamsPrepared for GPPL Leadership
Automation of the daily P&L to Gross Profit level is built and targeted to go live this week. Two workstreams open on Monday and now lead the sheet: Foreign Entity Scoping, beginning with finance reports, and MTM Inventory Aging, where the source data is already in place and the algorithm design is the next step. Across the established workstreams, the verified reports — Sales, Debtors, Inventory and Purchase — move to full automation, removing the manual sign-off that currently delays the daily upload, while Payables and Collection Target remain in build, both awaiting logic or data confirmation from the GPPL team.
1
Management P&L and P&L
GPPL membersPrabhat · Arjun Verma
#
Deliverable
Status
Progress
Dependency
Target
1.1
Daily P&L automation up to Gross Profit levelBuild complete. Go-live targeted within the reporting week.
Ready for Go-Live
90%
Go-live confirmation from GPPL Finance
24–28 Aug
1.2
Accuracy validation of automated P&L against ERPExpected accuracy: Revenue ~98%; Gross Profit 85–90%.
In Progress
60%
ERP data availability
24–28 Aug
1.3
Month-end variance analysis and reconciliationRecurring month-end activity, owned by the Finance Team.
Not Started
0%
Item 1.1 go-live
Month-end
2
Foreign Entity Scoping
GPPL membersAbbasi
#
Deliverable
Status
Progress
Dependency
Target
2.1
Scope of first phase — finance reportsAgreed to begin with finance reports before extending further.
Complete
100%
—
Closed
2.2
Discovery calls with individual entitiesCalls with the various entities commence Monday.
Scheduled
0%
Entity availability
From Mon 24 Aug
2.3
Way-forward planUpdate on the way-forward plan due by the end of next week.
Not Started
0%
Item 2.2 calls
By 28 Aug
3
MTM Inventory Aging
GPPL membersAnil Keswani · Joydeep · Prabhat
#
Deliverable
Status
Progress
Dependency
Target
3.1
Source data — inventory and purchase costingPrabhat onlyRaw inventory and purchase costing data already loaded in the SI system.
Complete
100%
—
Closed
3.2
Algorithm design sessionWorking session on the design of the aging algorithm.
Scheduled
0%
—
Mon 24 Aug
3.3
Algorithm build and validationTimeline to be set once the algorithm design is agreed on Monday.
Not Started
0%
Item 3.2 design agreement
To be set
4
Verify & Commit
GPPL membersPrabhat · Arjun Verma
#
Deliverable
Status
Progress
Dependency
Target
4.1
Decision to fully automate verified reports (Sales, Debtors, Inventory, Purchase)Agreed. Removes the manual sign-off currently required before daily upload.
Complete
100%
—
Closed
4.2
Remove manual sign-off from the daily upload pipelineEliminates the present dependency and delays in pushing verified reports.
In Progress
70%
Item 4.1 decision (closed)
24–28 Aug
4.3
Reversal mechanism for committed dataCommitted data remains reversible where a correction is required later.
In Progress
60%
—
24–28 Aug
5
Debtors & Sales Distribution
GPPL membersPrabhat · Arjun Verma
Incremental data only — base Debtors and Sales pages are covered under Workstream 4.
#
Deliverable
Status
Progress
Dependency
Target
5.1
Automated upload pipelinePipeline built and ready.
Complete
100%
—
Closed
5.2
Data accuracy validationValidation currently in progress with the GPPL team.
In Progress
50%
GPPL validation sign-off
24–28 Aug
6
Payables / Vendor Aging / MSME
GPPL membersPrabhat · Arjun Verma
#
Deliverable
Status
Progress
Dependency
Target
6.1
Vendor Aging report buildFile received from GPPL; development under way.
In Progress
40%
Source file received
24–28 Aug
6.2
Vendor Master buildFile received from GPPL; development under way.
In Progress
40%
Source file received
24–28 Aug
6.3
Scroll Report buildFile received from GPPL; development under way.
In Progress
40%
Source file received
24–28 Aug
6.4
MSME — ERP issue resolution+ ApraERP issues currently being sorted, expected resolved by end of next week. MSME can be brought into scope once closed.
In Progress
25%
ERP fixes at GPPL
By 28 Aug
7
Collection Target & Bank Collection
GPPL membersPrabhat · Arjun Verma
#
Deliverable
Status
Progress
Dependency
Target
7.1
ERP raw report extraction — automationRaw report from the ERP is automated.
Complete
100%
—
Closed
7.2
Derivation logic and formulas for the usable reportBeing worked out jointly with the GPPL team.
In Progress
50%
GPPL confirmation of calculation logic
24–28 Aug
7.3
Test reports for Collection Target and Bank CollectionNext step. To be prepared on our reading of the agreed logic.
Not Started
0%
Item 7.2 logic
24–28 Aug
7.4
Validation sign-off on values, calculations and logicTest reports to be shared with GPPL for confirmation.