Status & progress update

Financial Dashboard — Delivery Tracker

As at 21 August 2026 Target completion Wk 34 · 24–28 Aug 2026 22 line items · 7 workstreams Prepared for GPPL Leadership

Automation of the daily P&L to Gross Profit level is built and targeted to go live this week. Two workstreams open on Monday and now lead the sheet: Foreign Entity Scoping, beginning with finance reports, and MTM Inventory Aging, where the source data is already in place and the algorithm design is the next step. Across the established workstreams, the verified reports — Sales, Debtors, Inventory and Purchase — move to full automation, removing the manual sign-off that currently delays the daily upload, while Payables and Collection Target remain in build, both awaiting logic or data confirmation from the GPPL team.

1

Management P&L and P&L

GPPL membersPrabhat · Arjun Verma
#DeliverableStatus Progress DependencyTarget
1.1 Daily P&L automation up to Gross Profit levelBuild complete. Go-live targeted within the reporting week. Ready for Go-Live 90% Go-live confirmation from GPPL Finance 24–28 Aug
1.2 Accuracy validation of automated P&L against ERPExpected accuracy: Revenue ~98%; Gross Profit 85–90%. In Progress 60% ERP data availability 24–28 Aug
1.3 Month-end variance analysis and reconciliationRecurring month-end activity, owned by the Finance Team. Not Started 0% Item 1.1 go-live Month-end
2

Foreign Entity Scoping

GPPL membersAbbasi
#DeliverableStatus Progress DependencyTarget
2.1 Scope of first phase — finance reportsAgreed to begin with finance reports before extending further. Complete 100% Closed
2.2 Discovery calls with individual entitiesCalls with the various entities commence Monday. Scheduled 0% Entity availability From Mon 24 Aug
2.3 Way-forward planUpdate on the way-forward plan due by the end of next week. Not Started 0% Item 2.2 calls By 28 Aug
3

MTM Inventory Aging

GPPL membersAnil Keswani · Joydeep · Prabhat
#DeliverableStatus Progress DependencyTarget
3.1 Source data — inventory and purchase costingPrabhat onlyRaw inventory and purchase costing data already loaded in the SI system. Complete 100% Closed
3.2 Algorithm design sessionWorking session on the design of the aging algorithm. Scheduled 0% Mon 24 Aug
3.3 Algorithm build and validationTimeline to be set once the algorithm design is agreed on Monday. Not Started 0% Item 3.2 design agreement To be set
4

Verify & Commit

GPPL membersPrabhat · Arjun Verma
#DeliverableStatus Progress DependencyTarget
4.1 Decision to fully automate verified reports (Sales, Debtors, Inventory, Purchase)Agreed. Removes the manual sign-off currently required before daily upload. Complete 100% Closed
4.2 Remove manual sign-off from the daily upload pipelineEliminates the present dependency and delays in pushing verified reports. In Progress 70% Item 4.1 decision (closed) 24–28 Aug
4.3 Reversal mechanism for committed dataCommitted data remains reversible where a correction is required later. In Progress 60% 24–28 Aug
5

Debtors & Sales Distribution

GPPL membersPrabhat · Arjun Verma

Incremental data only — base Debtors and Sales pages are covered under Workstream 4.

#DeliverableStatus Progress DependencyTarget
5.1 Automated upload pipelinePipeline built and ready. Complete 100% Closed
5.2 Data accuracy validationValidation currently in progress with the GPPL team. In Progress 50% GPPL validation sign-off 24–28 Aug
6

Payables / Vendor Aging / MSME

GPPL membersPrabhat · Arjun Verma
#DeliverableStatus Progress DependencyTarget
6.1 Vendor Aging report buildFile received from GPPL; development under way. In Progress 40% Source file received 24–28 Aug
6.2 Vendor Master buildFile received from GPPL; development under way. In Progress 40% Source file received 24–28 Aug
6.3 Scroll Report buildFile received from GPPL; development under way. In Progress 40% Source file received 24–28 Aug
6.4 MSME — ERP issue resolution+ ApraERP issues currently being sorted, expected resolved by end of next week. MSME can be brought into scope once closed. In Progress 25% ERP fixes at GPPL By 28 Aug
7

Collection Target & Bank Collection

GPPL membersPrabhat · Arjun Verma
#DeliverableStatus Progress DependencyTarget
7.1 ERP raw report extraction — automationRaw report from the ERP is automated. Complete 100% Closed
7.2 Derivation logic and formulas for the usable reportBeing worked out jointly with the GPPL team. In Progress 50% GPPL confirmation of calculation logic 24–28 Aug
7.3 Test reports for Collection Target and Bank CollectionNext step. To be prepared on our reading of the agreed logic. Not Started 0% Item 7.2 logic 24–28 Aug
7.4 Validation sign-off on values, calculations and logicTest reports to be shared with GPPL for confirmation. Not Started 0% Item 7.3 test reports 24–28 Aug